Jaiprakash Associates Limited (JAL) - Wish Town Noida
Knight's Court KGT 1-8 (RERA Registered):
Physical progress of balance works duringĀ  Jun'21
No. Task Name Physical progress % for Jun 2021
KGT-1 KGT-2 KGT-3 KGT-4 KGT-5 KGT-6 KGT-7 KGT-8
    Balance at end of May'21 Planned in Jun'21 Achieved in Jun'21 Balance at end of May'21 Planned in Jun'21 Achieved in Jun'21 Balance at end of May'21 Planned in Jun'21 Achieved in Jun'21 Balance at end of May'21 Planned in Jun'21 Achieved in Jun'21 Balance at end of May'21 Planned in Jun'21 Achieved in Jun'21 Balance at end of May'21 Planned in Jun'21 Achieved in Jun'21 Balance at end of May'21 Planned in Jun'21 Achieved in Jun'21 Balance at end of May'21 Planned in Jun'21 Achieved in Jun'21
1 Civil Works
1.1 Mumty M/c Room 100% 8% 0% 100% 8% 0 100% 8% 0% 96% 8% 0% 100% 10% 0% 100% 5% 0% 100% 5% 0% 100% 5% 0%
1.2 Overhead Water Tank 67% 10% 0% 68% 10% 0% 100% 10% 0% 100% 10% 0% 100% 10% 0% 100% 5% 0% 100% 5% 0% 100% 5% 0%
1.3 Grinding & rendering of external surface including primer and painting 77% 12% 1% 86% 10% 20% 81% 10% 4% 75% 10% 1% 76% 10% 10% 100% 10% 8% 89% 10% 11% 93% 10% 11%
1.4 Balance Civil/Mech. work for lift installation 83% 10% 25% 100% 10% 0% 86% 7% 2% 90% 7% 0% 100% 5% 0% 100% 5% 0% 67% 10% 0% 71% 10% 0%
1.5 Common area works of the tower (incl. entrance lobby/reception, corridor and staircase) 92% 5% 2% 97% 5% 0% 98% 5% 3% 94% 5% 1% 100% 5% 1% 93% 5% 3% 89% 5% 3% 93% 5% 5%
1.6 Brick Work 25% 10% 0% 50% 15% 0% 100% 10% 0% 100% 12% 0% Comp - - 17% 10% 17% 33% 10% 0% 50% 20% 0%
1.7 Door Frames 75% 10% 0% 100% 10% 0% 100% 5% 0% 100% 5% 0% 100% 10% 0% 100% 10% 0% 100% 10% 0% 100% 10% 0%
1.8 Internal Plaster 80% 10% 0% 67% 8% 0% 0% 0% 0% 0% 0% 0% 38% 10% 0% 86% 8% 14% 100% 10% 29% 100% 8% 0%
1.9 Tiling/ Stone/IPS works 89% 5% 4% 97% 5% 0% 98% 5% 1% 90% 5% 0% 99% 5% 0% 100% 5% 0% 99% 5% 0% 100% 5% 0%
1.10 Installation of Main Door & utility doors to make flats lockable 100% 0% 0% 100% 0% 0% 100% 0% 0% 75% 0% 0% 100% 0% 0% 100% 0% 0% 100% 0% 0% 100% 0% 0%
1.11 Lift installation incl. cladding works of lift lobby and associated electrical works 100% 0% 0% 100% 0% 0% 100% 0% 0% 99% 0% 0% 100% 0% 0% 100% 0% 0% 100% 0% 0% 100% 0% 0%
1.12 Basement Civil Works (incl. white wash and parking works) 74% 5% 19% 88% 5% 19% 96% 6% 4% 96% 6% 9% 93% 5% 17% 87% 5% 20% 58% 10% 10% 60% 6% 12%
2 Plumbing & Fire Fighting Works
2.1 Plumbing framework for downtake water supply 74% 10% 17% 100% 8% 18% 97% 9% 16% 79% 8% 0% 100% 7% 0% 100% 7% 0% 80% 6% 4% 88% 5% 3%
2.2 Plumbing works for uptake water supply 98% 0% 3% 100% 0% 0% 100% 0% 0% 91% 0% 0% 100% 0% 0% 100% 0% 0% 100% 0% 0% 100% 0% 0%
2.3 Sewerage works (vertical and horizontal) 87% 8% 0% 100% 5% 3% 85% 7% 5% 93% 7% 0% 100% 7% 8% 100% 7% 0% 100% 6% 0% 100% 5% 0%
2.4 Fire fighting sprinkler work 42% 12% 25% 100% 8% 35% 74% 7% 16% 100% 5% 0% 100% 8% 0% 100% 8% 0% 100% 8% 0% 100% 7% 0%
3 Fire Related Works
3.1 Basement Ventilation Works 100% 0% 0% 100% 0% 0% 100% 0% 0% 100% 0% 0% 100% 0% 0% 100% 0% 0% 100% 0% 0% 100% 0% 0%
4 Electrical Works
4.1 clearance/laying of conduits with fish wire and boxes 100% 10% 0% 100% 8% 0% 97% 7% 0% 100% 7% 0% 92% 5% 12% 97% 5% 25% 100% 5% 6% 100% 5% 0%
4.2 Basement Electrical lighting 100% 0% 0% 100% 0% 0% 100% 0% 0% 100% 0% 0% 100% 0% 0% 100% 0% 0% 100% 0% 0% 100% 0% 0%
5 Aluminium works
5.1 Aluminium works (Frames, Shutters, Glass & Hardware) 99% 5% 0% 100% 0% 0% 100% 0% 0% 92% 0% 0% 100% 0% 0% 100% 0% 0% 100% 0% 0% 100% 0% 0%
6 External Development
6.1 External development works ( incl. plumbing, drainage and sewarage connections, landscape, etc 100% 0% 0% 100% 0% 0% 100% 0% 0% 100% 0% 0% 100% 0% 0% 100% 0% 0% 100% 0% 0% 100% 0% 0%
Note:- 1. Progress in the sheet has been considered till 30th Jun
2. % Balance is based on the relative balance works at the time of start of this Project (i.e. 20th Feb) and not in absolute
3. Progress at site got hampered due to lock down/curfew imposed by Govt in wake of ongoing 2nd wave of pandemic Covid-19



Jaiprakash Associates Limited (JAL) - Wish Town Noida
Knight's Court KGT 1-8 (RERA Registered):
Balance works planned during Jul'21
No. Task Name Planned % for Jul 2021
KGT-1 KGT-2 KGT-3 KGT-4 KGT-5 KGT-6 KGT-7 KGT-8
    Balance at end of June'21 Planned in July'21 Balance at end of June'21 Planned in July'21 Balance at end of June'21 Planned in July'21 Balance at end of June'21 Planned in July'21 Balance at end of June'21 Planned in July'21 Balance at end of June'21 Planned in July'21 Balance at end of June'21 Planned in July'21 Balance at end of June'21 Planned in July'21
1 Civil Works
1.1 Mumty M/c Room 100% 8% 100% 8% 100% 8% 96% 8% 100% 9% 100% 5% 100% 5% 100% 5%
1.2 Overhead Water Tank 67% 10% 68% 10% 100% 10% 100% 10% 100% 10% 100% 5% 100% 5% 100% 5%
1.3 Grinding & rendering of external surface including primer and painting 76% 10% 66% 10% 77% 10% 74% 10% 66% 10% 92% 10% 77% 10% 81% 10%
1.4 Balance Civil/Mech. work for lift installation 58% 10% 100% 10% 83% 7% 90% 7% 100% 6% 100% 10% 67% 10% 71% 10%
1.5 Common area works of the tower (incl. entrance lobby/reception, corridor and staircase) 90% 5% 97% 6% 94% 5% 93% 5% 99% 5% 89% 6% 86% 5% 87% 5%
1.6 Brick Work 25% 10% 50% 13% 100% 10% 100% 12% comp - comp - 33% 10% 50% 10%
1.7 Door Frames 75% 10% 100% 10% 100% 5% 100% 5% 100% 10% 100% 10% 100% 10% 100% 10%
1.8 Internal Plaster 80% 10% 67% 8% 0% 0% comp - 38% 10% 71% 10% 71% 10% 100% 8%
1.9 Tiling/ Stone/IPS works 85% 5% 97% 5% 97% 5% 89% 5% 99% 5% 100% 5% 99% 5% 99% 5%
1.10 Installation of Main Door & utility doors to make flats lockable 100% 0% 100% 0% 100% 0% 75% 0% 100% 0% 100% 0% 100% 0% 100% 0%
1.11 Lift installation incl. cladding works of lift lobby and associated electrical works 100% 0% 100% 0% 100% 0% 99% 0% 100% 0% 100% 0% 100% 0% 100% 0%
1.12 Basement Civil Works (incl. white wash and parking works) 56% 5% 69% 8% 92% 6% 87% 6% 77% 7% 67% 8% 48% 10% 48% 6%
2 Plumbing & Fire Fighting Works
2.1 Plumbing framework for downtake water supply 57% 8% 82% 10% 80% 10% 79% 10% 100% 7% 100% 7% 75% 6% 85% 5%
2.2 Plumbing works for uptake water supply 95% 0% 100% 0% 100% 0% 91% 0% 100% 0% 100% 0% 100% 0% 100% 0%
2.3 Sewerage works (vertical and horizontal) 87% 8% 97% 7% 81% 6% 93% 6% 93% 7% 100% 7% 100% 6% 100% 5%
2.4 Fire fighting sprinkler work 17% 12% 65% 10% 58% 7% 100% 8% 100% 8% 100% 10% 100% 8% 100% 7%
3 Fire Related Works
3.1 Basement Ventilation Works 100% 0% 100% 0% 100% 0% 100% 0% 100% 0% 100% 0% 100% 0% 100% 0%
4 Electrical Works
4.1 clearance/laying of conduits with fish wire and boxes 100% 10% 100% 8% 97% 7% 100% 6% 81% 5% 72% 5% 94% 5% 100% 5%
4.2 Basement Electrical lighting 100% 0% 100% 0% 100% 0% 100% 0% 100% 0% 100% 0% 100% 0% 100% 0%
5 Aluminium works
5.1 Aluminium works (Frames, Shutters, Glass & Hardware) 99% 5% 100% 0% 100% 0% 92% 0% 100% 0% 100% 0% 100% 0% 100% 0%
6 External Development
6.1 External development works ( incl. plumbing, drainage and sewarage connections, landscape, etc 100% 0% 100% 0% 100% 0% 100% 0% 100% 0% 100% 0% 100% 0% 100% 0%
Note:- 1. % Balance is based on the relative balance works at the time of start of this Project (i.e. 20th Feb) and not in absolute terms