Jaiprakash Associates Limited (JAL) - Wish Town Noida
Knight's Court KGT 1-8 (RERA Registered):
Physical progress of balance works during Dec'22
No. Task Name Physical progress % for Dec'22
KGT-1 KGT-2 KGT-3 KGT-4 KGT-5 KGT-6 KGT-7 KGT-8
    Balance at end of Nov'22 Planned in Dec'22 Achieved in Dec'22 Balance at end of Nov'22 Planned in Dec'22 Achieved in Dec'22 Balance at end of Nov'22 Planned in Dec'22 Achieved in Dec'22 Balance at end of Nov'22 Planned in Dec'22 Achieved in Dec'22 Balance at end of Nov'22 Planned in Dec'22 Achieved in Dec'22 Balance at end of Nov'22 Planned in Dec'22 Achieved in Dec'22 Balance at end of Nov'22 Planned in Dec'22 Achieved in Dec'22 Balance at end of Nov'22 Planned in Dec'22 Achieved in Dec'22
1 Civil Works
1.1 Mumty M/c Room 50% 5% 50% 67% 4% 33% 10% 6% 0% 20% 8% 6% Comp - - 5% 5% 0% 50% 7% 10% 29% 7% 14%
1.2 Overhead Water Tank 28% 4% 0% 35% 5% 32% 13% 5% 0% 25% 7% 0% Comp - - 5% 5% 0% 33% 5% 7% 33% 7% 17%
1.3 Grinding & rendering of external surface including primer and painting 35% 4% 9% 46% 3% 9% 43% 5% 8% 34% 5% 4% 24% 6% 6% 20% 5% 3% 18% 7% 4% 18% 5% 5%
1.4 Balance Civil/Mech. work for lift installation Comp - - 8% 5% 8% 8% 4% 0% 9% 4% 0% Comp - - 3% 3% 0% 2% 2% 2% 4% 4% 4%
1.5 Common area works of the tower (incl. entrance lobby/reception, corridor and staircase) 22% 4% 2% 33% 5% 5% 24% 5% 5% 30% 4% 2% 24% 4% 10% 25% 5% 2% 27% 5% 11% 28% 5% 12%
1.6 Brick Work Comp - - Comp - - Comp - - Comp - - Comp - - Comp - - 33% 5% 0% Comp - -
1.7 Door Frames 25% 6% 25% 33% 6% 33% 7% 4% 7% 40% 8% 40% Comp - - Comp - - 29% 7% 0% Comp - -
1.8 Internal Plaster 20% 6% 20% Comp - - Comp - - Comp - - 13% 5% 0% 14% 5% 14% 29% 6% 0% Comp - -
1.9 Tiling/ Stone/IPS works 9% 5% 9% 15% 6% 8% 61% 4% 9% 54% 4% 11% 8% 5% 4% 35% 5% 9% 38% 4% 14% 52% 5% 7%
1.10 Installation of Main Door & utility doors to make flats lockable Comp - - 8% 5% 8% 100% 8% 35% 100% 8% 38% 100% 6% 50% 100% 6% 0% 100% 5% 24% 100% 5% 25%
1.11 Lift installation incl. cladding works of lift lobby and associated electrical works 3% 3% 3% 7% 5% 1% 17% 5% 3% 47% 7% 30% 13% 5% 7% 25% 5% 8% 7% 5% 3% 10% 5% 7%
1.12 Basement Civil Works (incl. white wash and parking works) 43% 4% 2% 46% 5% 0% 75% 4% 9% 61% 4% 6% 55% 3% 4% 53% 4% 2% 41% 4% 0% 42% 4% 0%
2 Plumbing & Fire Fighting Works
2.1 Plumbing framework for downtake water supply Comp - - Comp - - 4% 3% 0% 5% 3% 0% 3% 2% 2% 2% 2% 2% 6% 3% 0% 9% 4% 0%
2.2 Plumbing works for uptake water supply 9% 5% 0% 11% 5% 0% 6% 4% 0% 15% 5% 0% 18% 6% 2% 23% 5% 3% 43% 6% 14% 43% 5% 3%
2.3 Sewerage works (vertical and horizontal) Comp - - Comp - - 8% 5% 0% 8% 5% 0% 3% 2% 2% 2% 2% 2% 8% 5% 0% 10% 6% 0%
2.4 Fire fighting sprinkler work 4% 4% 2% 3% 2% 0% 8% 3% 0% 3% 2% 0% 3% 2% 3% 3% 3% 3% 5% 4% 0% 3% 2% 0%
3 Fire Related Works
3.1 Basement Ventilation Works 10% 10% 10% 30% 20% 20% 40% 20% 40% 40% 10% 40% 60% 10% 50% 50% 10% 30% 60% 10% 50% 70% 10% 50%
4 Electrical Works
4.1 clearance/laying of conduits with fish wire and boxes 10% 7% 10% 10% 7% 10% 18% 6% 13% 19% 7% 16% 12% 4% 4% 16% 7% 11% 19% 5% 11% 18% 7% 12%
4.2 Basement Electrical lighting 53% 6% 33% 50% 4% 30% 67% 5% 42% 70% 4% 45% 100% 5% 50% 100% 5% 50% 100% 0% 40% 95% 0% 35%
5 Aluminium works
5.1 Aluminium works (Frames, Shutters, Glass & Hardware) 47% 5% 13% 57% 5% 17% 65% 4% 8% 66% 5% 8% 69% 4% 11% 61% 4% 5% 67% 4% 14% 65% 4% 11%
6 External Development
6.1 External development works ( incl. plumbing, drainage and sewarage connections, landscape, etc 41% 5% 10% 45% 5% 14% 53% 3% 16% 59% 3% 14% 62% 3% 27% 57% 4% 22% 53% 4% 18% 51% 4% 16%
Note:- 1. Progress in the sheet has been considered till 31st Decv'22
2. % Balance is based on the relative balance works at the time of start of this Project (i.e. 20th Feb'21) and not in absolute terms



Jaiprakash Associates Limited (JAL) - Wish Town Noida
Knight's Court KGT 1-8 (RERA Registered):
Balance works planned during Jan'23
No. Task Name Planned % for Jan' 2023
KGT-1 KGT-2 KGT-3 KGT-4 KGT-5 KGT-6 KGT-7 KGT-8
    Balance at end of Dec'22 Planned in Jan'23 Balance at end of Dec'22 Planned in Jan'23 Balance at end of Dec'22 Planned in Jan'23 Balance at end of Dec'22 Planned in Jan'23 Balance at end of Dec'22 Planned in Jan'23 Balance at end of Dec'22 Planned in Jan'23 Balance at end of Dec'22 Planned in Jan'23 Balance at end of Dec'22 Planned in Jan'23
1 Civil Works
1.1 Mumty M/c Room Comp - 33% 12% 10% 6% 14% 8% Comp - 5% 5% 40% 7% 14% 7%
1.2 Overhead Water Tank 28% 8% 3% 3% 13% 7% 25% 7% Comp - 5% 5% 27% 5% 17% 7%
1.3 Grinding & rendering of external surface including primer and painting 26% 6% 37% 9% 34% 7% 30% 5% 17% 6% 17% 5% 14% 7% 13% 5%
1.4 Balance Civil/Mech. work for lift installation Comp - Comp - 8% 4% 9% 4% Comp - 3% 3% Comp - Comp -
1.5 Common area works of the tower (incl. entrance lobby/reception, corridor and staircase) 20% 4% 28% 5% 19% 5% 27% 4% 27% 5% 23% 5% 16% 5% 16% 5%
1.6 Brick Work Comp - Comp - Comp - Comp - Comp - Comp - 33% 5% Comp -
1.7 Door Frames Comp - Comp - Comp - Comp - Comp - Comp - 29% 7% Comp -
1.8 Internal Plaster Comp - Comp - Comp - Comp - 13% 5% Comp - 29% 6% Comp -
1.9 Tiling/ Stone/IPS works Comp - 7% 6% 51% 4% 43% 4% 5% 5% 26% 5% 23% 4% 45% 5%
1.10 Installation of Main Door & utility doors to make flats lockable Comp - Comp - 65% 8% 63% 8% 50% 6% 100% 6% 76% 5% 75% 5%
1.11 Lift installation incl. cladding works of lift lobby and associated electrical works Comp - 5% 5% 13% 5% 17% 7% 7% 5% 17% 5% 3% 3% 3% 3%
1.12 Basement Civil Works (incl. white wash and parking works) 41% 10% 46% 10% 67% 6% 56% 6% 51% 6% 52% 4% 41% 4% 42% 4%
2 Plumbing & Fire Fighting Works
2.1 Plumbing framework for downtake water supply Comp - Comp - 4% 3% 5% 3% Comp - 1% 1% 6% 3% 9% 4%
2.2 Plumbing works for uptake water supply 9% 5% 11% 5% 6% 4% 15% 5% 16% 6% 21% 5% 29% 6% 40% 5%
2.3 Sewerage works (vertical and horizontal) Comp - Comp - 8% 5% 8% 5% 2% 2% 1% 1% 8% 5% 10% 6%
2.4 Fire fighting sprinkler work 2% 2% 3% 2% 8% 3% 3% 2% Comp - Comp - 5% 4% 3% 2%
3 Fire Related Works
3.1 Basement Ventilation Works Comp - 10% 10% Comp - Comp - 10% 10% 20% 10% 10% 10% 20% 10%
4 Electrical Works
4.1 clearance/laying of conduits with fish wire and boxes Comp - Comp - 5% 5% 3% 3% 8% 4% 5% 5% 8% 5% 6% 6%
4.2 Basement Electrical lighting 20% 10% 20% 10% 25% 10% 25% 10% 50% 5% 50% 5% 60% 5% 60% 5%
5 Aluminium works
5.1 Aluminium works (Frames, Shutters, Glass & Hardware) 35% 5% 39% 5% 58% 4% 58% 5% 58% 4% 57% 4% 53% 4% 54% 4%
6 External Development
6.1 External development works ( incl. plumbing, drainage and sewarage connections, landscape, etc 31% 5% 32% 5% 37% 3% 45% 3% 36% 3% 36% 4% 34% 4% 35% 4%
Note:- 1. % Balance is based on the relative balance works at the time of start of this Project (i.e. 20th Feb'21) and not in absolute terms