Jaiprakash Associates Limited (JAL) - Wish Town Noida Kalypso Court KT - 7, 8, 11, 12 (RERA Registered):
Physical progress of balance works during Jun'21
No. Task Name Physical progress % for June 2021
KT-7 KT-8 KT-11 KT-12
    Balance at end of May'21 Planned in Jun'21 Achieved in Jun'21 Balance at end of May'21 Planned in Jun'21 Achieved in Jun'21 Balance at end of May'21 Planned in Jun'21 Achieved in Jun'21 Balance at end of May'21 Planned in Jun'21 Achieved in Jun'21
1 Civil Works
1.1 Mumty M/c Room Comp - - Comp - - Comp - - Comp - -
1.2 Overhead Water Tank Comp - - Comp - - Comp - - 10% 5% 0%
1.3 Grinding & rendering of external surface including primer and painting 21% 5% 1% 22% 6% 2% 18% 5% 0% 44% 7% 5%
1.4 Balance Civil/Mech. work for lift installation Comp - - Comp - - 2% 2% 0% 2% 2% 0%
1.5 Common area works of the tower (incl. entrance lobby/reception, corridor and staircase) 9% 4% 1% 35% 5% 1% 24% 6% 7% 34% 7% 6%
1.6 Brick Work Comp - - Comp - - Comp - - Comp - -
1.7 Door Frames Comp - - Comp - - Comp - - Comp - -
1.8 Internal Plaster Comp - - Comp - - Comp - - Comp - -
1.9 Tiling/ Stone/IPS works 34% 6% 11% 56% 5% 2% 51% 5% 6% 56% 7% 2%
1.10 Installation of Main Door & utility doors to make flats lockable 59% 10% 16% 77% 10% 0% Comp - - 41% 10% 29%
1.11 Lift installation incl. cladding works of lift lobby and associated electrical works 2% 2% 2% 39% 8% 13% 35% 8% 10% 3% 3% 0%
1.12 Basement Civil Works (incl. white wash and parking works) 66% 6% 2% 60% 6% 1% 30% 4% 0% 34% 5% 2%
2 Plumbing & Fire Fighting Works
2.1 Plumbing framework for downtake water supply 3% 3% 1% 58% 6% 1% 70% 6% 22% 40% 7% 10%
2.2 Plumbing works for uptake water supply 51% 6% 20% 76% 6% 3% 66% 7% 11% 59% 6% 8%
2.3 Sewerage works (vertical and horizontal) 4% 4% 4% 33% 8% 4% 43% 6% 5% 52% 7% 0%
2.4 Fire fighting sprinkler work Comp - - Comp - - Comp - - Comp - -
3 Fire Related Works
3.1 Basement Ventilation Works 5% 0% 5% 5% 0% 5% 15% 0% 0% 16% 0% 0%
4 Electrical Works
4.1 clearance/laying of conduits with fish wire and boxes Comp - - Comp - - 6% 6% 0% 5% 5% 0%
4.2 Basement Electrical lighting 80% 10% 0% 80% 10% 0% 40% 15% 5% 40% 15% 5%
4.3 Rising Mains 30% 30% 10% 40% 20% 10% 30% 10% 10% 30% 30% 5%
5 Aluminium works
5.1 Aluminium works (Frames, Shutters, Glass & Hardware) 66% 5% 8% 70% 6% 14% 68% 5% 5% 63% 5% 2%
6 External Development
6.1 External development works ( incl. plumbing, drainage and sewarage connections, landscape, etc 44% 5% 0% 34% 5% 0% 100% 6% 0% 100% 6% 0%
Note:- 1. Progress in the sheet has been considered till 30th Jun
2. Progress at site got hampered due to lock down/curfew imposed by Govt in wake of ongoing 2nd wave of pandemic Covid-19
3. Based on the progress, 3rd demand of payment for KT-7,8,11 & 12 & 4th demand for KT-7 customers is due in May'21.



Kalypso Court KT - 7, 8, 11, 12 (RERA Registered):
Balance works planned during July'21
No. Task Name Planned % for July 2021
KT-7 KT-8 KT-11 KT-12
    Balance at end of Jun'21 Planned in July'21 Balance at end of Jun'21 Planned in July'21 Balance at end of Jun'21 Planned in July'21 Balance at end of Jun'21 Planned in July'21
1 Civil Works
1.1 Mumty M/c Room Comp - Comp - Comp - Comp -
1.2 Overhead Water Tank Comp - Comp - Comp - 10% 5%
1.3 Grinding & rendering of external surface including primer and painting 19% 5% 20% 6% 18% 5% 39% 7%
1.4 Balance Civil/Mech. work for lift installation Comp - Comp - 2% 2% 2% 2%
1.5 Common area works of the tower (incl. entrance lobby/reception, corridor and staircase) 8% 4% 34% 5% 17% 6% 28% 7%
1.6 Brick Work Comp - Comp - Comp - Comp -
1.7 Door Frames Comp - Comp - Comp - Comp -
1.8 Internal Plaster Comp - Comp - Comp - Comp -
1.9 Tiling/ Stone/IPS works 23% 6% 54% 5% 45% 5% 54% 7%
1.10 Installation of Main Door & utility doors to make flats lockable 43% 10% 77% 10% Comp - 12% 10%
1.11 Lift installation incl. cladding works of lift lobby and associated electrical works 0% 2% 26% 8% 25% 8% 3% 3%
1.12 Basement Civil Works (incl. white wash and parking works) 64% 6% 59% 6% 30% 4% 33% 5%
2 Plumbing & Fire Fighting Works
2.1 Plumbing framework for downtake water supply 2% 3% 57% 6% 48% 6% 30% 7%
2.2 Plumbing works for uptake water supply 31% 6% 72% 6% 55% 7% 52% 6%
2.3 Sewerage works (vertical and horizontal) Comp - 29% 8% 38% 6% 52% 7%
2.4 Fire fighting sprinkler work Comp - Comp - Comp - Comp -
3 Fire Related Works
3.1 Basement Ventilation Works Comp - Comp - 15% 0% 16% 0%
4 Electrical Works
4.1 clearance/laying of conduits with fish wire and boxes Comp - Comp - 6% 6% 5% 5%
4.2 Basement Electrical lighting 80% 10% 80% 10% 35% 15% 35% 15%
4.3 Rising Mains 20% 30% 30% 20% 20% 10% 25% 30%
5 Aluminium works
5.1 Aluminium works (Frames, Shutters, Glass & Hardware) 57% 5% 55% 6% 63% 5% 61% 5%
6 External Development
6.1 External development works ( incl. plumbing, drainage and sewarage connections, landscape, etc 44% 5% 34% 5% 100% 6% 100% 6%
Note:- 1. % Balance is based on the relative balance works at the time of start of this Project (i.e. 18th Sep) and not in absolute terms