Klassic Heights
Description of Tower Construction Stage Next Month Planning
Klassic KD1 Internal plaster and flooring is in progress Internal plaster and flooring will continue
Klassic KD2 Brickwork and plaster in progress Brickwork and plaster will continue
Klassic KD3 Brickwork and plaster in progress Brickwork and plaster will continue
Klassic KNG 1 Brickwork and plaster in progress Brickwork and plaster will be in progress
Klassic KNG 2 Brickwork and plaster in progress Brickwork and plaster will be in progress
Klassic KNG 3 Casting of 16th FRS in progress casting of 17th FRS will be completed
Klassic IB  KI 1 Internal plaster and flooring is in progress Internal plaster and flooring will continue
Klassic IB  KI 2 Internal plaster and flooring is in progress Internal plaster and flooring will continue
Klassic D1 /KO1 Internal plaster and flooring is in progress Internal plaster and flooring will continue
Klassic D2 /KO2 Internal plaster and flooring is in progress Internal plaster and flooring will continue
Klassic D3 Casting of 21st FRS is completed Brickwork and plaster will be in progress
Klassic D4 Casting of 16th FRS in progress casting of 17th FRS will continue
Klassic D5 Casting of 16th FRS in progress casting of 17th FRS will continue
Klassic D6 Casting of 18th FRS is completed casting of 19th FRS will be completed