Kalypso Court
Description of Tower Construction Stage Next Month Planning
Kalypso Court -1 Tower ready for possession Completion of formalities in progress
Kalypso Court-2 Tower ready for possession Completion of formalities in progress
Kalypso Court-3 Finishing works in progress Finishing works will continue
Kalypso Court-4 Finishing works in progress Finishing works will continue
Kalypso Court-5 Finishing works in progress Finishing works will continue
Kalypso Court-6 Brickwork, plaster and flooring is in progress Brickwork, plaster and flooring will continue
Kalypso Court-7 Brickwork, plaster and flooring is in progress Brickwork, plaster and flooring will continue
Kalypso Court-8 Brickwork, plaster and flooring is in progress Brickwork, plaster and flooring will continue
Kalypso Court-9 Plaster and flooring works are in progress Plaster and flooring works will continue
Kalypso Court-10 Plaster and flooring works are in progress Plaster and flooring works will continue
Kalypso Court-11 Plaster and flooring is in progress Plaster and flooring will continue
Kalypso Court-12 Plaster and flooring is in progress Plaster and flooring will continue
Kalypso Court-14 Finishing activities in progress Finishing activities will continue
Kalypso Court-15 Finishing works are in progress Finishing works will continue
Kalypso Court-16 Handover to FMG in progress Keep tower ready for possession